ConcreteMetric Navigation Menu
Temporary Works for Concrete Construction – Guide 2026 | ConcreteMetric
Concrete Construction Guide 2026

Temporary Works for Concrete Construction – Guide

Complete guide to formwork, falsework, shoring, propping, and bracing for concrete construction

Understand the full scope of temporary works in concrete construction — types, design principles, loading requirements, safe installation procedures, and removal sequences for formwork, falsework, and shoring systems in 2026.

Formwork Systems
Falsework & Shoring
Design Loads
Safe Removal

🏗️ Temporary Works for Concrete Construction

Essential knowledge for structural engineers, site managers, formwork contractors, and concrete specialists in 2026

✔ What Are Temporary Works?

Temporary works in concrete construction are structures, systems, and components that are erected to support and shape freshly placed concrete until it achieves sufficient strength to be self-supporting. They include formwork (the mould that gives concrete its shape), falsework (the load-bearing framework that supports formwork from below), and shoring and propping systems (temporary supports for existing structures during construction). Temporary works are designed, installed, loaded, and then safely stripped once concrete reaches its design strength — making their correct specification and management critical to structural integrity and site safety.

✔ Why Temporary Works Matter

Temporary works failures account for a significant proportion of serious construction site accidents and structural collapses. The loads imposed on falsework during a concrete pour — fresh concrete self-weight (approximately 24 kN/m³), dynamic pour pressure, construction live loads, and impact — can be far greater than the permanent loads the finished structure will carry. A falsework system that is undersized, incorrectly braced, set up on weak ground, or stripped before concrete has cured adequately can collapse catastrophically. Temporary works must be formally designed, independently checked, and managed under a dedicated Temporary Works Coordinator in line with current standards.

✔ Scope of Temporary Works in 2026

Modern temporary works for concrete construction cover a broad scope: column and wall formwork, slab and beam soffit formwork, slipform and jumpform systems for tall cores, bridge deck falsework, re-shoring and back-propping for multi-storey construction, and excavation support such as sheet piling and soil nailing. Each system has distinct design requirements, material options, and removal procedures. This guide covers all primary temporary works types used in concrete construction, with practical reference data and load tables for 2026.

Understanding Temporary Works for Concrete Construction

Temporary works are fundamentally different from permanent structures — they are built to serve a construction purpose and then dismantled, yet they must withstand loads that are often heavier and more dynamic than those carried by the finished building. During a typical concrete slab pour, the soffit formwork and its supporting falsework must resist the full wet concrete pressure, which increases with pour rate and height. For a 300mm slab poured at a rate of 1 m/hour, the hydrostatic pressure at the base of a 3m wall can reach 72 kN/m² — requiring a properly designed system of soldiers, walings, ties, and props to safely contain and support the fresh mix.

All temporary works for concrete construction in Australia are governed by AS 3610 (Formwork for Concrete) and the National Construction Code. In the UK, the relevant standards are BS EN 12812 (Falsework) and BS 5975 (Temporary Works). In the US, ACI 347 provides guidance on formwork for concrete. Regardless of jurisdiction, the core principle is the same: temporary works must be designed by a competent engineer, inspected before concrete placement, and only stripped when concrete has reached the required minimum stripping strength — typically confirmed by cube or cylinder testing. For more on assessing concrete strength, see our guide on Assessing Existing Concrete Structures.

📐 Key Temporary Works Design Parameters – Concrete Construction

Fresh Concrete Unit Weight: ~24 kN/m³ (2,400 kg/m³)
Hydrostatic Pressure (walls): P = ρ × g × H (kN/m²) | where H = pour height (m)
Lateral Pressure (ACI 347 walls): P = 7.2 + [785R / (T + 17.8)] kPa (R = pour rate m/hr, T = temp °C)
Slab Formwork Load: Dead (concrete) + Live (workers/equipment) + Dynamic Impact
Typical Live Load (soffit): Min. 2.4 kPa (workers + equipment)
Minimum Stripping Strength: Typically 75% of f'c for non-critical members; 100% for props/re-shores
Re-shoring Rule: At least 2 floors re-shored below active pour for multi-storey construction

🏗️ Typical Wall Formwork Assembly – Temporary Works Cross-Section

🟫 Fresh Concrete (Wet) Self-weight ~24 kN/m³ — hydrostatic lateral pressure on form face
🟠 ★ FORM FACE / SHEATHING ★ Plywood, steel plate, or plastic — direct contact with concrete
⬛ Walings (Horizontal Backing) Timber or steel — span between soldiers, transfer load to ties/props
🔵 Soldiers / Studs (Vertical Members) Primary vertical support — transfer load from form face to walings
⚙️ Tie Rods / Push-Pull Props / Kickers Through-ties resist lateral pressure; props provide alignment stability
📋 Sole Plates / Base Plates Distribute loads to ground; prevent point loads on slab or subbase
🌍 Ground / Structural Slab Support Must be assessed for bearing capacity before falsework erection
24 kN/m³ Wet Concrete
Unit Weight
72 kN/m² Lateral Pressure
3m Wall Height
75% f'c Min. Stripping
Strength
≥2 Floors Re-shoring Below
Active Pour

Wall formwork assembly showing the load path from wet concrete pressure (orange layer) through form face, walings, soldiers, ties, and down to the ground support. Every component must be designed for the full hydrostatic pressure at the base of the pour.

Types of Temporary Works in Concrete Construction

Temporary works for concrete construction span a wide range of systems, each suited to specific structural elements, pour heights, construction programs, and reuse requirements. Selecting the right system affects both safety and cost — proprietary modular systems cost more per unit but are faster to erect and have engineered load ratings, while traditional timber formwork is flexible and low-cost but requires more skilled labour and careful design. The table below provides a reference comparison of all major temporary works types used in concrete construction in 2026.

Temporary Works Type Application Primary Material Max. Typical Height / Load Reuse Cycles Key Standard
Timber Wall Formwork Walls, columns, footings Structural plywood + timber soldiers Up to 4m pour height 5–15 uses AS 3610 / ACI 347
Proprietary Panel Formwork Walls, columns, large pours Steel or aluminium frames + ply/steel face Up to 6m+ with stacking 100–200+ uses AS 3610 / BS EN 12812
Soffit / Slab Formwork Suspended slabs, beam soffits Plywood + timber / aluminium joists Variable — prop-supported 10–30 uses AS 3610 / ACI 347
Modular Aluminium Soffit Suspended slabs, repetitive floors Aluminium frame + ply decking Prop-limited (up to 6m) 500–1000+ uses Manufacturer SWL rating
Falsework / Shoring Towers High-level slabs, bridges, transfer beams Steel tube & coupler or proprietary frame 20m+ towers possible 100+ uses BS EN 12812 / AS 3610
Adjustable Steel Props (Acrow) Slab soffit propping, re-shoring Steel tube — adjustable extension 1.0m – 4.5m height; 30–80 kN SWL 200+ uses BS EN 1065
Slipform System Vertical concrete cores, silos, chimneys Steel forms + hydraulic jacking Continuous vertical — unlimited height Specialist system — reused by contractor ACI 313 / specialist design
Jumpform / Climbing Form Tall building cores, shear walls Steel platform + form panels, crane-lifted Repetitive floor-by-floor — unlimited Project-specific reuse Specialist engineer design
Tunnel Form (Table Form) Repetitive cellular buildings Steel U-frame — walls + slab in one pour Standard floor heights (2.4–3.2m) 500+ uses Manufacturer SWL + engineer design
Stay-in-Place (Permanent) Formwork Slabs, retaining walls, bridge decks Steel decking, GRP, precast concrete Span-dependent N/A — permanent AS 2327 / AS/NZS 4600

Temporary Works Types – Quick Reference

Timber Wall FormworkUp to 4m height
Proprietary Panel FormworkUp to 6m+ height
Soffit / Slab FormworkProp-supported
Modular Aluminium Soffit500–1000+ reuses
Falsework / Shoring Towers20m+ towers
Adjustable Steel Props (Acrow)30–80 kN SWL
Slipform SystemUnlimited height
Jumpform / Climbing FormFloor-by-floor
Tunnel Form (Table Form)500+ reuses
Stay-in-Place FormworkPermanent — no strip

Temporary Works Design – Loads and Structural Principles

Designing temporary works for concrete construction requires accounting for multiple simultaneous load cases. Unlike permanent structures, temporary works must be designed for the worst-case construction condition — not the serviceability condition — and the loads applied during construction are often more severe than those in the finished structure. A transfer beam falsework may carry the entire weight of the wet concrete above while being erected on a slab that is still curing from the floor below, requiring careful back-propping analysis and progressive stripping sequences.

⚖️ Dead Load — Wet Concrete

The primary dead load on formwork and falsework is the self-weight of fresh concrete at approximately 24–25 kN/m³ (reinforced mix). For a 200mm slab, this is 4.8–5.0 kN/m² applied uniformly to the soffit form. For walls, the load acts as lateral hydrostatic pressure increasing with depth — not as a vertical gravity load. Both load directions must be designed for simultaneously in wall formwork design.

👷 Live Load — Construction Activity

AS 3610 and ACI 347 require a minimum construction live load of 2.4 kPa (50 psf) on slab soffit formwork to account for workers, tools, and reinforcement placement. Where concrete buggies, bobcats, or concrete pumps operate on the formwork deck, higher point loads apply — typically 4.8–9.6 kPa. Live loads act simultaneously with dead loads and must be combined in the design load case.

💨 Lateral Loads — Wind & Impact

Tall formwork assemblies — particularly free-standing column forms and wall forms — must be designed for wind loads during erection, concrete placement, and standing-empty periods. AS 1170.2 and BS EN 1991-1-4 provide wind load calculation methods for temporary structures. In addition, impact loads from concrete being discharged from a skip or pump pipe can be significant and are typically taken as an additional 2–4 kPa dynamic factor applied to the form face area.

🌊 Concrete Pressure — Walls & Columns

The maximum lateral pressure of fresh concrete against vertical formwork depends on pour rate, concrete temperature, use of retarders, and vibration depth. At slow pour rates (under 1 m/hour) and warm temperatures, concrete stiffens quickly and pressure stabilises below full hydrostatic. At rapid pour rates or with retarders, full hydrostatic pressure must be assumed: P = 24H kPa (where H is the pour height in metres). A 5m column poured rapidly generates 120 kPa — requiring heavily engineered yoke or clamp systems.

🏗️ Ground Bearing & Foundation

Falsework loads must be transmitted to ground or to an existing slab through sole plates and base plates that distribute concentrated prop loads over a sufficient bearing area. Before erecting any falsework, the ground bearing capacity must be assessed and confirmed adequate. On existing slabs, the slab's capacity to carry construction loads must be verified by an engineer — particularly important in multi-storey re-shoring situations where loads stack through multiple floors. For guidance on foundation assessment, see our guide on Backfilling Around Concrete Foundations.

📐 Deflection & Camber Control

Formwork deflection affects the finished concrete surface. AS 3610 limits deflection of form face panels to L/270 or 3mm, whichever is lesser, to maintain surface quality and dimensional accuracy. In beam and slab formwork, pre-camber is often applied to falsework to compensate for elastic deflection under wet concrete loads, ensuring the finished soffit is level after stripping. Deflection calculations must account for both beam bending and prop compression under full design load.

💡 Temporary Works Coordinator (TWC) — The Key Role in 2026

Under BS 5975:2019 (UK) and equivalent standards internationally, all significant temporary works in concrete construction must be managed by a designated Temporary Works Coordinator (TWC). The TWC is responsible for ensuring temporary works are correctly designed (or procured from a proprietary supplier with adequate design briefs), checked independently, issued with a permit to load, supervised during construction operations, and only stripped after a formal permit-to-strip has been issued. The TWC role is distinct from the engineer of record for the permanent works — temporary works require their own dedicated management pathway. Failure to appoint a competent TWC is a leading cause of temporary works failures on construction sites.

Formwork Materials — Comparison and Selection

The choice of formwork material directly affects concrete surface finish, construction speed, cost, and the number of reuses achievable from each form. The correct material depends on the structural element type, the specified concrete finish quality, the programme duration, and whether the project is one-off or repetitive. Understanding material properties allows engineers and site managers to specify and procure the most cost-effective and safe temporary works system for each application.

Plywood Form Face — Standard Sheathing

Structural plywood — typically 17mm or 21mm form-grade (F14 or F17 in Australia, B/BB in Europe) — is the most widely used formwork sheathing material. It is lightweight, easy to cut and fix, produces a smooth or textured finish depending on grade, and provides good spanning capability between secondary timber or aluminium bearers. Standard structural plywood achieves 5–15 reuses before surface degradation affects concrete finish quality. High-density overlay (HDO) plywood extends reuse to 30–50 cycles. Plywood must be sealed at edges and stored flat off the ground between uses.

Steel Formwork — High Reuse Applications

Steel form panels — typically 3–5mm thick mild steel plate welded to a RHS frame — provide 100–200+ reuses and a consistent class 2 concrete finish. Steel formwork is used where high repetition justifies the higher capital cost: bridge piers, tunnel linings, precast production, and repetitive column grids in tall buildings. Steel forms are heavier than aluminium or timber equivalents and require crane handling for larger panels. They must be kept clean, lightly oiled between pours, and repaired promptly when dented to prevent surface imperfections transferring to the concrete face.

Aluminium Formwork — Speed and Repetition

Proprietary aluminium formwork systems (e.g., Meva, Doka, PERI, RMD Kwikform) combine high reuse (500–1,000+ cycles), light weight (typically 30–40% lighter than equivalent steel), and precise factory engineering with integrated tie systems, push-pull props, working platforms, and lifting points. Initial procurement or hire cost is higher than timber, but total cost per m² of formed concrete is substantially lower on repetitive multi-storey projects. Aluminium formwork requires trained erection crews and must be handled carefully to avoid distortion of the aluminium extrusions.

⚠️ Critical Temporary Works Safety Rules — Never Compromise

The following rules must never be overridden on site: (1) Never strip formwork or remove props based on elapsed time alone — concrete strength must be confirmed by cube or cylinder testing before stripping. Warm weather may accelerate strength gain; cold weather can delay it significantly. (2) Never overload formwork by placing more concrete than the design pour rate allows, or by using mobile plant that exceeds the design live load. (3) Never remove mid-pour props or re-shores without engineer approval — losing a prop mid-pour can trigger progressive collapse. (4) Never erect falsework on ground that has not been assessed for bearing capacity. (5) Always obtain a formal permit to load before placing concrete and a permit to strip before removing formwork. These procedural controls — not just the structural design — are what prevent temporary works collapses.

Temporary Works Installation – Step-by-Step Process

Correct installation sequence is as critical as structural design for temporary works in concrete construction. A perfectly designed falsework system that is erected out of sequence, on unsuitable ground, or without adequate bracing can fail before concrete is even placed. The following steps apply to a typical slab and beam soffit formwork installation.

  • Step 1 — Prepare and check the design: Obtain the approved temporary works design from the engineer. Confirm it has been independently checked. Receive the design brief and ensure all site-specific parameters (slab thickness, pour height, concrete grade, pour rate) match the design assumptions.
  • Step 2 — Assess the support surface: Check ground bearing capacity or structural slab capacity for falsework loads. Install sole plates sized to spread prop point loads within allowable bearing pressure. Do not erect falsework on recently disturbed fill or frozen ground without specific engineering approval.
  • Step 3 — Erect primary props and ledgers: Install adjustable steel props or falsework towers plumb and at the spacings specified in the design. Fix ledger beams (primary bearers) at the correct height using the prop forks or head plates. Check all props are fully engaged and locked before loading.
  • Step 4 — Install secondary bearers and joists: Place secondary timber or aluminium joists across the ledgers at the design spacing. Confirm span and spacing match the plywood sheathing's allowable load capacity.
  • Step 5 — Fix form face sheathing: Lay and fix plywood or proprietary panel sheathing to secondary joists. Tape joints if a Class 2 or better concrete finish is required. Apply release agent evenly to the form face using a roller or spray — do not apply to reinforcement.
  • Step 6 — Install edge forms and kickers: Fix edge boards and kickers at slab perimeters and beam sides. Check all slab edge forms are plumb and at the correct finished floor level. Fix column and wall kickers to the hardened concrete below.
  • Step 7 — Fix reinforcement and services: Place steel reinforcement, post-tensioning ducts, conduits, and cast-in items per structural drawings. Ensure cover blocks are correctly placed and bar positions are within tolerance. The formwork must support the full weight of reinforcement plus wet concrete.
  • Step 8 — Pre-pour inspection (Permit to Load): The Temporary Works Coordinator must inspect the completed formwork assembly against the design drawings before concrete is placed. Issue a signed permit to load only when the assembly is confirmed compliant — checking plumb, level, prop positions, bracing, tie rods, and edge form stability.
  • Step 9 — Place concrete within design parameters: Pour concrete at the approved rate and maximum height per design. Monitor formwork during the pour for movement, bulging, or settlement. Stop the pour immediately if any movement is detected.
  • Step 10 — Cure and test: Allow concrete to cure to the minimum stripping strength. Take cube or cylinder samples and test at the specified age. Do not strip based on time alone — confirm strength by test results.
  • Step 11 — Strip under permit (Permit to Strip): Issue a permit to strip when strength test results confirm the minimum stripping strength has been achieved. Strip soffit forms first from mid-span toward supports. Never remove all props simultaneously — strip progressively to avoid shock loading. Retain re-shores where specified until the slab achieves full design strength.

✅ Temporary Works Quick Reference — Concrete Construction 2026

  • Wet concrete unit weight: ~24 kN/m³ — primary load on formwork and falsework
  • Minimum slab soffit live load: 2.4 kPa (workers + equipment) per AS 3610 / ACI 347
  • Minimum stripping strength: Typically 75% of f'c for non-critical elements — confirm by testing
  • Re-shoring: Minimum 2 floors below active pour for multi-storey construction
  • Key standard (AUS): AS 3610 Formwork for Concrete
  • Key standard (UK): BS EN 12812 Falsework + BS 5975 Temporary Works Procedures
  • Key standard (US): ACI 347 Guide to Formwork for Concrete
  • TWC role: Temporary Works Coordinator must be appointed for all significant temporary works
  • Permit to load + permit to strip: Mandatory formal checks before placing concrete and before striking

Frequently Asked Questions – Temporary Works for Concrete Construction

What are temporary works in concrete construction?
Temporary works in concrete construction are all structures, systems, and components installed to support, shape, and retain fresh concrete until it gains sufficient strength to be self-supporting. They include formwork (the mould that shapes concrete), falsework (the load-bearing framework supporting formwork from below), adjustable steel props and shoring towers (for re-shoring existing slabs), and ancillary items such as ties, walings, soldiers, and working platforms. Temporary works are designed to carry construction loads safely — including wet concrete weight, construction live loads, wind, and impact — and are removed (stripped) once the concrete has achieved the specified minimum strength.
What is the difference between formwork and falsework?
Formwork is the mould — the surface that is in direct contact with fresh concrete and gives it its shape. It includes the form face (plywood, steel, or plastic sheathing), edge forms, and any patterned or textured liners. Falsework is the load-bearing structural system that supports the formwork from below — props, towers, ledgers, bearers, and their foundations. Falsework carries the full weight of the formwork plus wet concrete plus construction live loads and transfers them safely to the ground or existing structure. Formwork shapes; falsework supports. Both must be designed for the same construction loads, but they serve different structural functions.
When can formwork be stripped from concrete?
Formwork should only be stripped when the concrete has achieved the minimum stripping strength specified in the temporary works design or in the project specification — not based on elapsed time alone. For most non-critical elements, stripping typically occurs at 75% of the 28-day design strength (f'c). Soffit forms and props carrying significant loads may require the full 28-day strength before removal. Concrete strength must be confirmed by cube or cylinder testing from samples taken at the pour. Factors that delay strength gain include cold weather, high water-cement ratio, use of supplementary cementitious materials (SCMs) such as fly ash or GGBS, and inadequate curing. Stripping prematurely is one of the primary causes of concrete slab and beam failures.
What is re-shoring and back-propping in multi-storey construction?
Re-shoring (or back-propping) is the practice of installing temporary props beneath slabs that have already been stripped, to transfer construction loads from slabs being poured above through the building frame to lower levels or to ground. In multi-storey concrete construction, the new slab being poured cannot carry its own wet concrete weight plus that of the floors above — it requires support from the floors below through a chain of re-shores. The standard requirement is a minimum of two floors re-shored below the active pour level, though the engineer of record must verify this for each specific project. Re-shores must be installed plumb, fully engaged, and checked before each pour above them.
What is the maximum lateral pressure of concrete on formwork?
The maximum lateral pressure of fresh concrete against vertical formwork is governed by the pour rate, concrete temperature, and whether chemical retarders are used. If concrete is poured very slowly and the temperature is warm, the concrete will begin to stiffen (set) before full hydrostatic pressure develops. However, at rapid pour rates or low temperatures, full hydrostatic pressure must be assumed: P = ρgh = 24 × H kPa, where H is the pour height in metres. For example, a 3m wall poured rapidly gives 72 kPa at the base. ACI 347R provides a more refined formula: for walls with normal plasticised concrete at 20°C and a pour rate of 2 m/hr, maximum pressure is approximately 48–60 kPa. Always use the most conservative applicable formula unless site-specific conditions justify a reduced pressure.
What is a slipform system used for?
A slipform system is a continuously moving formwork system used to construct tall vertical concrete elements such as building cores, lift shafts, silos, chimneys, bridge piers, and cooling towers. The formwork — typically 1.0–1.2m deep steel forms on both faces of the wall — is hydraulically jacked upward at a rate of 150–300mm per hour, continuously placing fresh concrete at the top while the partially cured concrete at the bottom is continuously exposed. A working platform rises with the formwork, allowing workers to place reinforcement, embed items, and monitor concrete quality. Slipform construction eliminates construction joints (producing a monolithic element), achieves very rapid vertical progress, and is cost-effective for repetitive cross-sections — but requires 24/7 continuous operations and expert management once started.
What does a Temporary Works Coordinator do?
A Temporary Works Coordinator (TWC) is a competent person appointed by the principal contractor to manage all aspects of temporary works on a project. Under BS 5975:2019 and similar international standards, the TWC is responsible for: receiving temporary works design briefs from the site team; appointing and instructing temporary works designers; ensuring all designs are independently checked; issuing permits to load before concrete placement; arranging inspection of completed temporary works assemblies; issuing permits to strip after stripping strength criteria are met; and maintaining a temporary works register for the project. The TWC does not necessarily design the temporary works themselves, but they oversee and coordinate the entire management process. Appointing a competent TWC is mandatory for all significant temporary works in UK construction and is best practice internationally.

Temporary Works Resources & Standards

📘 Key Standards for Temporary Works

Temporary works for concrete construction are governed by national and international standards: AS 3610 (Australia — Formwork for Concrete), BS EN 12812 (UK/Europe — Falsework Performance Requirements), BS 5975:2019 (UK — Code of Practice for Temporary Works Procedures), and ACI 347R (USA — Guide to Formwork for Concrete). These standards define design loads, material requirements, inspection procedures, and stripping criteria for safe temporary works construction in 2026.

Concrete Assessment Guide →

⚙️ Formwork Design Load Principles

Temporary works design must account for wet concrete dead loads (24 kN/m³), construction live loads (min. 2.4 kPa), wind loads on exposed forms, impact loads from concrete discharge, and hydrostatic pressure on vertical forms. Design loads are combined per the applicable load combination factors in AS 1170, BS EN 1990, or ASCE 7. Understanding the full load picture — not just the concrete weight — is what separates safe temporary works from systems that are technically undersized under real construction conditions.

Foundation Backfill Guide →

🏗️ Concrete Construction Best Practice

Successful concrete construction depends on the integration of mix design, reinforcement detailing, formwork engineering, and curing management. Temporary works sit at the intersection of all these disciplines — a correctly designed and safely managed formwork and falsework system is what transforms a structural design into a sound concrete element. Explore our full suite of concrete construction guides for in-depth coverage of every stage of the concrete construction process in 2026.

Air Entrained Concrete Guide →